Construction crews continue work on the $21 million Green River Road Interchange Project. Construction crews will be working on the westbound SR-91 and on the Green River Road Bridge. Lane closures are required at both locations. Note that the time for the closure on Thursday night, April 10th, has been extended. Lane closure information for next week is as follows:
Tues – Th. 4/8 – 4/10
Green River Road Bridge
8 AM to 4 PM
1 northbound lane closed on the bridge
Thursday 4/10
Westbound SR-91
7 PM to 4 AM
2 lanes closed
(HOV and #1 lanes)